試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(7)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(7)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The project is close to completion. All project deliverable have been accepted by the stakeholders. The program manager has asked the project manager to take on another project. All external contracts have been met and all the contracts closed.What should the project manager do?
A、Announce the project is closed and move to the new project.
B、Ensure that all procedures to transfer the project’s products and service to production are in place.
C、Conduct an external review of the project by a team of experts.
D、Ensure the remaining project activities are transferred to the new project.