試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(4)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

You have always been asked by your management to cut your project estimate by ten percent after you have given it to them. The scope of your new project is unclear and there are over 30 stakeholders. Management expects a 25 percent reduction in downtime as a result of the project. Which of the following is the BEST course of action in this situation?
A、Re-plan to achieve a 35 percent improvement in downtime.
B、Reduce the estimates and note the changes in the risk response plan.
C、Provide an accurate estimate of the actual costs and be able to support it.
D、Meet with the team to identify where you can find lo percent savings.