試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(4)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Three months into a project, the project manager learns that the project has a CPI of 1.1 and a SPI of 0.84. Three months later the CPI and SPI have changed to 0.9 and 1.0, respectively.In the three month interval, what course of action was likely taken by the project manager?
A、Reduced project scope
B、Authorized contingency plan
C、Increased resources
D、Reduced resources