試題內(nèi)容

Within an organization, office politics have negatively impacted previous projects, consuming large amounts of stakeholder time. What should the project manager do at the start of the project to ensure the politics do not affect the current project ?
A、Seek sponsorship from senior management.
B、 Recommend a new project manager with proven capabilities in dealing with politics.
C、 Hire a third party project manager to avoid the politics inside the organization.
D、 Let the stakeholders select the right project manager for the project.