A project manager leads a project to build a data center. The client submits a dramatic change to the project manager. Insisting that modification must be introduced as soon as possible involves incremental changes to the budget and an expectation of the overall schedule. What should the project manager do next ?
A、Advise the client to initiate the change as another project.
B、Present the client’s request at the next change control board meeting.
C、Include the client’s change and re-baseline the budget and schedule.
D、Ignore the request as the baseline for the budget and schedule have been agreed to.